To take the ISQI CTAL-TA_Syll2019 exam, you must have already passed the ISTQB Foundation Level exam (CTFL) and the ISTQB Certified Tester Advanced Level - Test Manager (CTAL-TM) or the ISTQB Certified Tester Advanced Level - Technical Test Analyst (CTAL-TTA) exam. Additionally, it is recommended that you have at least 3-4 years of experience in software testing, preferably as a Test Analyst, as well as practical experience in applying software testing techniques and methods.


To prepare for the CTAL-TA_Syll2019 exam, candidates can take advantage of various training courses and study materials offered by ISQI and other reputable organizations. It is also recommended that candidates have some practical experience in software testing before taking CTAL-TA_Syll2019 exam. Passing the CTAL-TA_Syll2019 exam will not only validate your expertise in software testing but also enhance your professional credibility and open up new opportunities for career growth.

 

NEW QUESTION # 27
Consider the following requirement:
The system shall allow cash advances of at least 200 Euros for all supported credit cards The following credit cards are supported- American Express, Diners, VISA, Mastercard and Eurocard.
The requirement has been identified as business critical.
The following test conditions have been derived:
1. The system shall allow cash advances of at least 200 Euros
2. It shall support American Express, Diners, VISA, Mastercard and Eurocard.
Assume you are following a risk-based testing strategy, where likelihood and impact are both assessed on a five-point scale ranging from very low to very high The requirement R1 was identified as a risk item during the quality risk analysis process. In total 20 risk items were identified during thisprocess Assume that technical project stakeholders have assessed the likelihood of the requirementR1 risk item at a medium levelGiven only the information above, which of the following statements is true?

  • A. The test cases associated with requirement R1 shall be run first in the test execution period
  • B. A large number of test cases should be designed for requirement R1, based on impact
  • C. The test cases associated with requirement R1 must be run towards the middle of the test execution period.
  • D. The risk impact for requirement R1 should be categorized as high or very high

Answer: D


NEW QUESTION # 28
Which of the following is an appropriate task for the Test Analyst to perform during the test execution phase?

  • A. Creating automated tests
  • B. Finalizing test data and test environments
  • C. Analysing anomalies to establish their likely causes
  • D. Creating a test execution schedule

Answer: B


NEW QUESTION # 29
What type of testing would focus on completeness, appropriateness, and correctness characteristics of the application under test?

  • A. Reliability testing
  • B. Usability testing
  • C. Functional testing
  • D. Efficiency testing

Answer: C

Explanation:
Explanation
The correct answer isA.Functional testing.
Functional testing
Functional testing is the type of testing that focuses on completeness, appropriateness, and correctness characteristics of the application under test. Completeness means that all the functions and features of the application are tested. Appropriateness means that the functions and features are suitable for the intended purpose and meet the user'sneeds.Correctness means that the functions and features produce the expected results and do not contain any errors or defects1.
References=
* ISTQB Certified Tester Advanced Level Syllabus Technical Test Analyst2, Section 3.2.2 Functionality
* ISTQB Certified Tester Advanced Level Syllabus Test Analyst3, Section 3.2.2 Functionality
* ISTQB Test Analyst Syllabus and Study Guide4, Section 3.2.2 Functionality


NEW QUESTION # 30
Based on the tax system specification as described below, using boundary value analysis, which would be the best test set to explicitly test on single boundary value fully?
Tax system
A tax system needs to be updated due to new legislation. For a person with a salary of less than € 20 000 and who is married, the tax needs to be recalculated.
If a person has at least three and less than six children, an additional 10% reduction is applicable.

  • A. Test set (i)
  • B. Test set (iii)
  • C. Test set (iv)
  • D. Test set (ii)

Answer: B


NEW QUESTION # 31
To enhance both the effectiveness and efficiency of the test design phase, the purchase of a test design tool is being considered. Which one of these statements best characterizes a test design tool?

  • A. A test design tool enables individual tests to be traced to requirements
  • B. A test design tool validates models of the software.
  • C. A test design tool enables tests to be executed automatic ally.
  • D. A test design tool generates test inputs from requirements

Answer: B


NEW QUESTION # 32
You are working on a hand held product that will be used by carpet salespeople to create estimates while the salesperson is at the customer's location. The carpet installation prices are different based on how much carpet the customer will be buying. If the customer is buying enough only for a small room (less than 20 square yards) the cost to install is $5 a square yard. For a medium room (less than 40 square yards) the cost to install is $4 a square yard. For a large room (40 square yards or more) the cost to install is $2 a square yard. Two small rooms or one small room plus a set of stairs is priced at the medium room price. Two medium rooms or one medium room plus a set of stairs is priced at the large room price.
Which of the following is the smallest set of test conditions to provide minimum coverage of the boundary values?

  • A. 20 sq yds, 40 sq yds
  • B. O One small room, one medium room, one large room, one set of stairs, one large room + 1 set of stairs
  • C. No purchase, 1 sq yd, 20 sq yds, 40 sq yds, max sq yds
  • D. 0 sq yds, 1 sq yd, 19 sq yds, 20 sq yds, 39 sq yds, 40 sq yds, max sq yds, max sq yds + 1

Answer: D

Explanation:
Explanation
The smallest set of test conditions to provide minimum coverage of the boundary values is the one that tests the minimum and maximum values for each category of carpet installation prices, as well as the values that are just above or below the boundaries. Option A covers these values, as it tests the boundary values of 0, 20, and
40 square yards, as well as the values that are one square yard more or less than these boundaries. It also tests the maximum possible value for the carpet area and the value that exceeds it. The other options do not test all the boundary values or have redundant values. References =
* ISTQB Certified Tester Advanced Level Syllabus Technical Test Analyst1, page 2
* Boundary Value Analysis and Equivalence Partitioning Testing2, section "Boundary Value Analysis"
* Equivalence Partitioning Method3, section "Example 1: Equivalence and Boundary Value"


NEW QUESTION # 33
A new web site must operate correctly with different browsers (Internet Explorer, Google Chrome, Firefox, Opera, Safari), using different plug-ins (Realplayer, Mediaplayer), will be receiving pages from different servers (IIS, Apache and WebLogic) and will be running on various operating systems (Windows, Android, iOS and Linux).
Which of the following test techniques should you use to define the required test cases for testing this new web site in its variousenvironments?

  • A. Pairwise testing
  • B. Use case testing
  • C. Exploratory testing
  • D. Decision table testing

Answer: D


NEW QUESTION # 34
During which test stage is functional appropriateness typically tested?

  • A. System testing
  • B. Operability testing
  • C. Adaptability testing
  • D. Component testing

Answer: A

Explanation:
Explanation
Functional appropriateness is the degree to which a product or system provides functions that meet stated and implied needs when used under specified conditions1. It is typically tested during system testing, which is the process of testing an integrated system to verify that it meets specified requirements2. System testing is conducted after component testing and before acceptance testing, and it covers both functional and non-functional aspects of the system3. References = ISO 25010, section A.1; ISTQB Advanced Level Test Analyst Syllabus 2019, section 1.3.1; Test Automation Fundamentals, section A.1.


NEW QUESTION # 35
Consider the following requirement:
The system shall allow cash advances of at least 200 Euros for all supported credit cards The following credit cards are supported- American Express, Diners, VISA, Mastercard and Eurocard.
The requirement has been identified as business critical.
The following test conditions have been derived:
1. The system shall allow cash advances of at least 200 Euros
2. It shall support American Express, Diners, VISA, Mastercard and Eurocard.
Assume you are following a risk-based testing strategy, where likelihood and impact are both assessed on a five-point scale ranging from very low to very high The requirement R1 was identified as a risk item during the quality risk analysis process. In total 20 risk items were identified during this process Assume that technical project stakeholders have assessed the likelihood of the requirement R1 risk item at a medium level Given only the information above, which of the following statements is true?

  • A. The test cases associated with requirement R1 shall be run first in the test execution period
  • B. A large number of test cases should be designed for requirement R1, based on impact
  • C. The test cases associated with requirement R1 must be run towards the middle of the test execution period.
  • D. The risk impact for requirement R1 should be categorized as high or very high

Answer: D

Explanation:
Explanation
The risk impact is the measure of the potential negative consequences of a risk item on the project objectives.
It depends on the severity of the defect, the frequency of occurrence, and the visibility to the stakeholders.
Since requirement R1 is business critical, any failure in meeting this requirement would have a significant impact on the customer satisfaction, the reputation of the organization, and the legal compliance. Therefore, the risk impact for requirement R1 should be categorized as high or very high, regardless of the likelihood of occurrence. References =
* ISTQB Certified Tester Advanced Level Syllabus Technical Test Analyst1, page 2
* Risk Based Testing: Approach, Matrix, Process & Examples2, section "Risk Impact Assessment"
* What is Risk Based Testing: With Best Practices3, section "Risk Impact Analysis"


NEW QUESTION # 36
A PIN entry component of an ATM system has been developed using the following state table:

Using the state transition test technique, how many 0-switch test cases are needed to achieve 100% 0-switch coverage?

  • A. 0
  • B. 1
  • C. 2
  • D. 3

Answer: C

Explanation:
Explanation
A 0-switch test case is a test case that covers one transition from one state to another. To achieve 100%
0-switch coverage, all the transitions in the state table must be tested. There are eight transitions in the state table, as shown by the arrows. Therefore, eight 0-switch test cases are needed. References =
* ISTQB Certified Tester Advanced Level Syllabus Technical Test Analyst1, page 2
* How to Design Test Cases Using State Transition Testing Technique?2, section "0-switch coverage"
* 0 and 1 - Switch Coverage in State Transition Testing?3, answer by Marco Filippone


NEW QUESTION # 37
You are assigned as a Senior Test Analyst to lead a project test team composed of business users. These users have extensive business knowledge, but no testing experience. There is another test team composed of in-sourced professional testers that will also be used for this project. Your business users will be assisting the project on a part-time basis. The development team is building an application using the "V-model" development lifecycle. Your company has automated testing tools and test management systems for use by dedicated test teams. What would be an effective method to employ your business users in your testing effort?

  • A. Provide them with high-level test charters to execute checklists of items to be tested. You may also provide criteria to assist in verifying the application under test.
  • B. Using their knowledge of the system, have them construct detailed state transition diagrams, then translate the information into detailed step-by-step test procedures.
  • C. With their knowledge of business rules, have them create a detailed decision table, then enter the resulting information into the test management system as step-by-step test cases.
  • D. Have your business testers create automated test scripts using available test tools to ensure that regression tests can be executed on a timely basis.

Answer: A

Explanation:
Explanation
This is an effective method to employ business users in your testing effort because it allows them to leverage their domain knowledge and experience without requiring them to have technical skills or testing tools. Test charters are high-level descriptions of the test objectives, scope, and approach that guide the testers to explore the system and report any issues they find. Test charters are flexible and can be adapted to different test levels and types. They are also suitable for the V-model development lifecycle, which emphasizes verification and validation at each stage of the development process1 References =
* ISTQB Advanced Level Test Analyst Syllabus 2019, Section 3.2.3.2, page 482
* Exploratory Testing: An Agile Approach | Software Testing Help3
* Exploratory Testing: What are Test Charters? | TestLodge Blog4


NEW QUESTION # 38
You have been provided with the following decision table that was used for smoke testing the previous release of a set of hotel reservation software.

During discussions with the Test Manager you agreed that software behavior focused on the date of reservation, especially as midnight approaches, presented additonal risk.
You need to add more tests to provide more thorough coverage of the test conditions. Which of the following techniques should you use to design more tests?

  • A. State transition
  • B. Portability
  • C. Boundary value analysis
  • D. Orthogonal Arrays

Answer: A

Explanation:
Explanation
State transition is a technique that analyzes the behavior of an application for different input conditions and how it changes from one state to another in response to events. It is useful for testing scenarios where the date of reservation is a critical factor that affects the system state and output1 References =
* ISTQB Advanced Level Test Analyst Syllabus 2019, Section 3.2.2.3, page 432
* State Transition Testing - Diagram & Technique (Example) - Guru993
* State Transition Testing - GeeksforGeeks4


NEW QUESTION # 39
Consider the following scenario for a metro fare system:
If you take the metro before 9:30 am or in the afternoon between 5:00 pm until 7:00 pm, you must pay full fare A saver ticket is available for metro rides between 9:30 am and 5:00 pm [both inclusive], and after 7:00 pm.
Which off the following test sets will provide the best equivalence partitioning coverage?

  • A. 9:30 am, 9:31 am, 4:59 pm, 5:00 pm, 8:00 pm
  • B. 9:30 am, 4:00 pm, 6:00 pm, 8 00 pm, 8:30 pm
  • C. 9:29 am, 5 01 pm, 7:30 pm, 7:31 pm, 8:00 pm
  • D. 8:00 am, 10:00 am, 5:15 pm, 7:01 pm, 11:00 pm

Answer: A

Explanation:
Explanation
Equivalence partitioning is a technique that divides the input domain into classes of data that are expected to behave similarly. The test sets should cover one value from each equivalence class, as well as the boundary values between them. The equivalence classes for the metro fare system are:
* Before 9:30 am (full fare)
* Between 9:30 am and 5:00 pm (saver ticket)
* Between 5:00 pm and 7:00 pm (full fare)
* After 7:00 pm (saver ticket)
The boundary values are 9:30 am, 5:00 pm, and 7:00 pm. Therefore, the test set that provides the best equivalence partitioning coverage is the one that includes one value from each equivalence class and the boundary values, which is option D. References =
* ISTQB Certified Tester Advanced Level Syllabus Technical Test Analyst1, page 2
* Boundary Value Analysis and Equivalence Partitioning Testing2, section "Equivalence Partitioning"
* Equivalence Partitioning Method3, section "Example 1: Equivalence and Boundary Value"


NEW QUESTION # 40
While performing system testing, you have discovered what you believe to be a defect. You have performed the following steps:
1. Compared actual with expected results
2. Logged actual results
3. Identified the specific versions tested as well as specific environment configurations
4. Logged information in the context of the level of testing and the strategy What other step should you perform at the time you are logging the incident?

  • A. Identify and log any new risks that have surfaced
  • B. Update the test automation to bypass the defect
  • C. Debug the code to determine the cause of the defect
  • D. None, you have taken all appropriate steps

Answer: A

Explanation:
Explanation
Incident logging and reporting is an important part of incident management, as it helps to document the incident details, communicate the incident status, and analyze the incident causes and impacts1. One of the steps in incident logging and reporting is to identify and log any new risks that have surfaced as a result of the incident2. This helps to assess the severity and priority of the incident, as well as to plan for risk mitigation and contingency actions3. Debugging the code and updating the test automation are not part of incident logging and reporting, but rather part of incident resolution and recovery4. None is not a valid answer, as there is always room for improvement in incident management5.
References = 1: 5 Steps to Create an Effective Incident Reporting Procedure 2: 12 Things To Include In An Incident Report Log (Full Guide) 3: Incident reporting procedure example and flow chart 4: What is incident management? Steps, tips, and best practices 5: Incident Management: Process, System, & Tools


NEW QUESTION # 41
You are a Test Analyst in the banking domain. You have received the following requirement: "The system shall allow cash advances of at least 200 Euros for all supported credit cards. The following credit cards are supported: American Express, Diners, Visa, Mastercard and Eurocard.
Which one of the findings described below is true regarding this requirement?

  • A. The requirement indicates potential performance problems.
  • B. The requirement indicates potential usability problems
  • C. The requirement is ambiguous in terms of supported cards.
  • D. The requirement is unclear in terms of advance limits.

Answer: D

Explanation:
Explanation
The requirement states that the system shall allow cash advances of at least 200 Euros, but it does not specify the maximum amount or the conditions for different cards. This could lead to confusion, inconsistency, and errors in the system's functionality and testing. The requirement should be more precise and define the exact limits and rules for each card type and scenario. References = ISTQBAdvanced Level Test Analyst Syllabus
2019, section 2.1.1; Requirement Analysis Templates & Techniques, section "Requirement Analysis Best Practices".


NEW QUESTION # 42
Although usability is an important aspect for a new planning system, due to availability constraints, the usability evaluation shall be performed without Which of the following is a usability technique that can be applied in this situation?

  • A. Usability lab sessions
  • B. Usability prototyping
  • C. Usability survey
  • D. Usability review, e.g., heuristic evaluation

Answer: D


NEW QUESTION # 43
Consider the following scenario for a metro fare system:
If you take the metro before 9:30 am or in the afternoon between 5:00 pm until 7:00 pm, you must pay full fare A saver ticket is available for metro rides between 9:30 am and 5:00 pm [both inclusive], and after 7:00 pm.
Which off the following test sets will provide the best equivalence partitioning coverage?

  • A. 9:30 am, 9:31 am, 4:59 pm, 5:00 pm, 8:00 pm
  • B. 9:29 am, 5 01 pm, 7:30 pm, 7:31 pm, 8:00 pm
  • C. 8:00 am, 10:00 am, 5:15 pm, 7:01 pm, 11:00 pm
  • D. 9:30 am, 4:00 pm, 6:00 pm, 8 00 pm, 8:30 pm

Answer: D


NEW QUESTION # 44
The following decision table shows the conditions/actions that are handled by the current system regarding taking credit cards for reservations.

The customer has decided that credit cards are too high risk and wants to change to accepting only debit cards.
Debit cards have to be valid and also require a valid PIN in order to be accepted. Debit cards require purchase amount approval in order to be accepted. Given these changes, how many test cases will be needed to provide
100% coverage of the decision table?

  • A. 0
  • B. 1
  • C. 2
  • D. 3

Answer: C

Explanation:
Explanation
A decision table is a technique that shows the possible combinations of conditions and actions for a given problem. To achieve 100% coverage of the decision table, all the combinations of conditions must be tested.
The decision table has four conditions: debit card valid, PIN valid, amount approved, and dates available. Each condition has two possible values: yes or no. Therefore, the number of test cases for the decisiontable is 2^4 =
16. However, some of these test cases are invalid or redundant, as they do not reflect the logic of the problem.
For example, if the debit card is not valid, then the PIN and the amount are irrelevant. Similarly, if the PIN is not valid, then the amount is irrelevant. Therefore, these test cases can be eliminated from the decision table.
After eliminating the invalid or redundant test cases, only eight test cases remain, as shown in the table below:
Table
Debit card valid
PIN valid
Amount approved
Dates available
Actions
No
No
No
No
Reject reservation
No
No
No
Yes
Reject reservation
No
No
Yes
No
Reject reservation
No
No
Yes
Yes
Reject reservation
Yes
No
No
No
Reject reservation
Yes
No
No
Yes
Reject reservation
Yes
No
Yes
No
Reject reservation
Yes
No
Yes
Yes
Reject reservation
Yes
Yes
No
No
Prompt for lower purchase
Yes
Yes
No
Yes
Prompt for lower purchase
Yes
Yes
Yes
No
Prompt for different date
Yes
Yes
Yes
Yes
Create reservation
References =
* ISTQB Certified Tester Advanced Level Syllabus Technical Test Analyst1, page 2
* Decision tables - IBM2, section "Decision table overview"


NEW QUESTION # 45
You are assigned to a test team to write test cases for their retail call center application. Your analysis estimates a need for approximately 2,000 test cases. Your test team consists of experienced business users, who have helped with testing on an on-going basis for several years. The application that you are assigned to test is continually being updated to meet market and customer requirements.
What is recommended in this situation?

  • A. Creating low-level test cases to minimize on-going maintenance efforts
  • B. Having business users create decision tables and state transition diagrams to assist in creating step-by-step test cases
  • C. Writing low-level test cases with step by step instructions so your non-professional testers can execute the test cases without error
  • D. Focusing on high-level test cases consisting mostly of guidelines of what should be tested

Answer: D


NEW QUESTION # 46
You are a Test Analyst in the banking domain. You have received the following requirement: "The system shall allow cash advances of at least 200 Euros for all supported credit cards. The following credit cards are supported: American Express, Diners, Visa, Mastercard and Eurocard.
Which one of the findings described below is true regarding this requirement?

  • A. The requirement is unclear in terms of advance limits.
  • B. The requirement indicates potential performance problems.
  • C. The requirement indicates potential usability problems
  • D. The requirement is ambiguous in terms of supported cards.

Answer: B